Aerial view of the Reno-Stead Airport taken from an aircraft flying overhead.

Information for pilots and users of Reno-Stead Airport.


The next phase of ramp construction will begin on June 26, 2023

The image below shows the two phases for this year’s ramp and taxiway reconstruction project.  The ramp phase (green) will start next Monday June 26 and is scheduled to be completed on or before Wednesday August 2.  The taxiway A phase (red) will start August 2 (or when phase one completes) and be finished by Wednesday August 23.  As in past years, each phase will be enclosed with lighted construction barricades.  During the second phase, TWY A3 will be closed for the duration. To get around construction to go east/west on TWY A there will be a taxi detour in place on the ramp.  During the first phase, there will also be work done on the infield north of TWY A and west of TWY A3 to improve drainage and smooth that area out.  This work will not impact the safety area for RWY 8/26.  The concrete parking pads will also be unavailable during phase one and have limited availability during phase two.

If you have any questions on any of this, please let me know.

Scott

2023 Reno-Stead Airport ramp construction project

Posted

in

by

Tags: