A quick update on construction. Sometime between 0600-0800 tomorrow (Tuesday 8/1) morning, phase one (ramp – green area) will be complete and the phase two work area will be closed off (red area). This area includes Twy A at the center ramp including Twy A2 (A2 will be unavailable for the duration of this phase). There will be a taxi “detour” onto the ramp around the closed portion of Twy A. Phase two work is scheduled to be completed by the end of August. The concrete parking pads at center ramp will remain closed to accommodate the taxi around for construction. Please use caution in the work areas.
Hope you are all having a good summer. If you have any questions, please let me know.
Scott