Phase 1 ramp construction at Stead starts Monday July 25. The map below shows the area of TWY A that will be closed from next Monday until the first week of September. Just like last year, there will be a taxi detour around construction that will be indicated with low profile barricades. Please use caution in this area for construction vehicles and activity. After Air Races, phase 2 of construction will be the ramp area south of phase 1 (map also attached). A larger construction display board and printouts of these maps will be available in the terminal lobby later this week. Phase two will end sometime around Halloween.
An additional construction project that will be starting in the next month or so, will be the application of sealants and slurry to several areas on the landside and airside of the airport. More to come on this as the details are finalized.
Any questions, please let me know. Have a great day!
Scott