Runway Construction Update – 7-17-2018

RHB’s anticipated schedule for the week of July 16, 2018 is as follows:

RHB has confirmed night work for this week

Monday:  0700 -1730 – RHB’s continuing work activities include – runway reconstruction in work area “A”, east and west of taxiway “C” and taxiways “A”, “A3”, and “A4”, placing CTB, runway paving, installing new drainage features.  Titan Electrical continues to install new electrical features throughout the project.

Monday: 21:00 to 05:00 – Penhall begins sawing and sealing operations in work area A.

Tuesday:  0700 -1730 – RHB’s continuing work activities include – runway reconstruction in work area “A”,  east and west of taxiway “C” and taxiways “A”, “A3”, and “A4”, placing CTB, runway paving, installing new drainage features. Titan Electrical continues to install new electrical features throughout the project.

Tuesday: 21:00 to 05:00 – Penhall continues sawing and sealing operations in work area A.

Wednesday:  0700 -1730 – RHB’s continuing work activities include – runway reconstruction in work area “A”,  east and west of taxiway “C” and taxiways “A”, “A3”, and “A4”, placing CTB, runway paving, installing new drainage features. Titan Electrical continues to install new electrical features throughout the project.

Wednesday: 21:00 to 05:00 – Penhall begins sawing and sealing operations west of work area B.

Thursday:  0700 -1730 – RHB’s continuing work activities will include  – runway reconstruction in work areas “A”, east and west of taxiway “C”, and taxiways “A”, “A3”, and “A4”,  placing CTB, runway paving, installing new drainage features.  Titan Electrical continues to install new electrical features throughout the project.

Thursday: 21:00 to 05:00 – Penhall continues sawing and sealing operations west of work area B.

Friday:  0700 -1730 – RHB’s continuing work activities will include  – runway reconstruction in work areas “A”, east and west of taxiway “C”, and taxiways “A” and “A3”, “A4”, placing CTB, runway paving, installing new drainage features.  Titan Electrical continues to install new electrical features throughout the project.

Friday: 21:00 to 05:00 – Penhall continues sawing and sealing operations west of work area B.

Saturday: 0700 -1730 – RHB’s continuing work activities will include  – runway reconstruction in work areas “A”, east and west of taxiway “C”, and taxiways “A” and “A3”, “A4”, placing CTB, installing new drainage features.

Runway 8-26 is closed and will remain closed until September 4, 2018.

Have a great day.